writing-plans

SKILL.md

Writing Plans

Quick Start

  1. Summarize - Executive summary with goals, non-goals, background
  2. Design - High-level approach, architecture diagram, key decisions
  3. Break Down - Tasks in 2-4 hour chunks with file locations
  4. Map Dependencies - Identify critical path and parallel opportunities
  5. Assess Risks - Likelihood x Impact matrix with mitigations
  6. Estimate - Three-point estimation with buffers

Features

Feature Description Guide
Plan Structure Comprehensive template Summary, design, tasks, testing, risks
Task Breakdown Manageable work units 2-4 hours, single owner, clear criteria
Dependency Mapping Sequence and parallelize Critical path, hard/soft dependencies
Risk Assessment Anticipate problems Likelihood x Impact matrix
Effort Estimation Realistic timing Three-point: (O + 4M + P) / 6
File-Level Detail Exact code locations New files, modifications, line numbers

Common Patterns

# Plan Structure
# Plan: [Feature Name]

## Metadata
- Status: Draft | Approved | In Progress
- Estimated Duration: [X days]
- Priority: P0 | P1 | P2

## Goals & Non-Goals
Goals: [What this WILL accomplish]
Non-Goals: [What this will NOT address]

## Design Overview
[High-level approach, architecture diagram]

## Implementation Tasks

### Phase 1: [Foundation] - [X days]
#### Task 1.1: [Name]
- Description: [What]
- Estimate: [X hours]
- Files: `src/file.ts:45-60`
- Dependencies: None
- Acceptance Criteria:
  - [ ] [Criterion 1]
  - [ ] [Criterion 2]

## Risks & Mitigations
| Risk | Likelihood | Impact | Mitigation |
|------|------------|--------|------------|
| [Risk] | High | High | [Strategy] |
# Dependency Diagram
           [START]
              |
   +----------+----------+
   |          |          |
[Task 1]  [Task 2]  [Task 3]  <- Parallel
   |          |          |
   +-----+----+          |
         |               |
      [Task 4]      [Task 5]
         |               |
         +-------+-------+
                 |
            [Task 6]      <- Integration
                 |
            [COMPLETE]

Critical Path: 1 -> 4 -> 6 (determines min duration)
# Effort Estimation
Three-Point: (Optimistic + 4*MostLikely + Pessimistic) / 6

Example - OAuth Implementation:
- Optimistic: 4 hours (works first try)
- Most Likely: 8 hours (normal dev)
- Pessimistic: 16 hours (issues)
Estimate = (4 + 32 + 16) / 6 = 8.7 hours

Buffers:
- Individual tasks: 20%
- Phase total: 30%
- Project total: 40%

Best Practices

Do Avoid
Keep tasks to 2-4 hour chunks Vague tasks ("implement feature")
Include exact file locations Skipping background/context
Specify clear acceptance criteria Ignoring non-functional requirements
Map dependencies explicitly Underestimating integration work
Build in buffer for unknowns Planning more than 2 weeks in detail
Include testing in the plan Hiding risks or uncertainties
Review plan with stakeholders Assuming requirements are complete
Update plan as you learn Forgetting rollback plans

Related Skills

  • executing-plans - Follow plans systematically
  • thinking-sequentially - Structure reasoning for plans
  • brainstorming-ideas - Generate options for plans
  • verifying-before-completion - Validate plan completion