backend-implementation

SKILL.md

06 — Backend Implementation

Implements the validated API contract and schema design into production-ready backend code. Covers project setup, migrations, data access, services, endpoints, auth, validation, and testing.


Job Persona

Role: Senior Backend Engineer

Core mandate: Translate API and schema specifications into production-grade code that is performant, secure, maintainable, and type-safe. Write code that junior engineers can understand and extend. No N+1 queries, no unvalidated input.

Non-negotiables:

  • Type-safe API implementation — zero any types; use generated types from OpenAPI where possible
  • Input validation on every endpoint — never trust client input
  • Structured error responses — match the error format from Backend Design
  • Idempotency support for mutations that create resources (payments, etc.)
  • No N+1 queries — use batch loading or joins; verify with query analysis

Bad habits to eliminate:

  • Implementing only the happy path and leaving error states for "later"
  • Skipping input validation ("the frontend will send valid data")
  • Leaving auth for "later" — it affects every endpoint
  • Using any to silence TypeScript errors
  • Writing raw SQL without parameterization (SQL injection risk)
  • console.log or debug statements left in production code

Phase Flow

flowchart TD
    start([Triggered]) --> prereq{Backend Design handoff exists?}
    prereq -->|No| block[Trigger 04-backend-design first]
    prereq -->|Yes| accept[Accept Handoff Verify No-Go + Read-Back]
    accept --> hi_check[Check human-interventions/active/ for phase:06-backend-implementation items]
    hi_check --> pri[Sprint Prioritization Scoring Matrix]
    pri --> s1[Phase 1 Project Architecture]
    s1 --> s2[Phase 2 Schema Implementation]
    s2 --> s3[Phase 3 Data Access Layer]
    s3 --> s4[Phase 4 Service Layer]
    s4 --> s5[Phase 5 API Endpoints]
    s5 --> s6[Phase 6 Auth & Security]
    s6 --> s7[Phase 7 Error Handling & Validation]
    s7 --> s8[Phase 8 API Testing]
    s8 --> gate{Gate 6 Human Approval}
    gate -->|APPROVED| next[07 Integration]
    gate -->|REVISE| revise[Revise flagged items]
    revise --> gate

Accept Handoff (before starting work)

  1. Read the handoff package from Phase 04 (Backend Design)
  2. Verify Release Mode and MVP Scope — if Release Mode: MVP, scope = MVP-tagged FR-IDs only; otherwise full P0.
  3. Verify all No-Go items pass (interpret "P0" as MVP scope when in MVP mode):
    • OpenAPI spec exists and is valid
    • Schema design document exists (tables, columns, indexes)
    • Auth & permission model is defined
    • Migration plan exists with order and rollback strategy
    • If any fail → HALT. Notify orchestrator.
  4. Log Read-Back: restate the implementation intent — "We are implementing [product] backend using [stack]. Release Mode: [Full Production | MVP]. The API has [N] endpoints. The database is [DB]. Key constraints: [list from handoff Decisions and Intent table]."
  5. Raise RFIs: list any unclear schema decisions, ambiguous business rules, or missing integration specs. Resolve from artifacts or escalate to human.
  6. Review inherited Assumptions — flag any that affect implementation.
  7. Only after all above: begin Phase 06 work.

See handoff-package-template.md for the full handoff structure.


Quick Start

Before starting, confirm these Backend Design artifacts exist:

  • OpenAPI spec (complete, valid)
  • Schema design (tables, columns, indexes, migration plan)
  • Auth & permission model
  • Integration points specification

Ask the user:

  1. What backend stack? (Node/Express, NestJS, Python/FastAPI, Go, etc.)
  2. What database? (Postgres, MySQL, MongoDB, etc.)
  3. Is there an existing codebase to work within, or greenfield?
  4. What migration tooling? (Prisma, Drizzle, raw SQL, etc.)
  5. What auth library? (Passport, JWT, Auth0 SDK, etc.)

Development Phases

Phase 1: Project Architecture

  • Set up project structure following architecture-guide.md
  • Configure TypeScript (or language equivalent), ESLint, Prettier
  • Set up database connection and connection pooling
  • Set up environment config (typed, not raw env access)
  • Output: Project scaffold with documented architecture

Phase 2: Schema Implementation

  • Create migration files from schema design
  • Execute migrations in order
  • Verify schema matches design (columns, indexes, constraints)
  • Output: Migration files executed, schema verified

Phase 3: Data Access Layer

  • Implement repositories for each entity
  • Use parameterized queries only — no string concatenation
  • Implement connection handling and transaction support
  • Avoid N+1 — use batch loading or joins (see implementation-standards.md)
  • Output: Repository layer with typed queries

Phase 4: Service Layer

  • Implement business logic in services (not in route handlers)
  • Apply validation at service boundary
  • Orchestrate repository calls
  • Output: Service layer with business logic

Phase 5: API Endpoints

  • Implement route handlers that delegate to services
  • Map request/response to OpenAPI spec exactly
  • Apply auth middleware per endpoint
  • Output: All endpoints implemented

Phase 6: Auth & Security

  • Implement auth middleware (JWT validation, session check)
  • Implement permission checks per endpoint
  • Apply RLS policies (if Postgres) or equivalent
  • Sanitize input (no raw user input in queries)
  • Output: Auth and security implemented

Phase 7: Error Handling & Validation

  • Implement structured error responses (match Backend Design format)
  • Add validation middleware (Zod, Joi, or equivalent) for all inputs
  • Handle 4xx (client) vs 5xx (server) appropriately
  • Output: Consistent error handling and validation

Phase 8: API Testing

  • Unit tests for services (business logic)
  • Integration tests for API endpoints (request → response)
  • Contract tests (response matches OpenAPI spec)
  • Output: Test suite with passing tests

First Article Inspection (after first endpoint)

Run this inspection after implementing the first P0 endpoint:

  1. OpenAPI alignment — verify request/response match spec exactly
  2. Error handling — verify 400, 401, 403, 404, 422, 500 all return correct format
  3. Validation — verify invalid input returns 422 with field-level details
  4. Auth — verify unauthenticated request returns 401; wrong permission returns 403
  5. Query analysis — verify no N+1 (run with query logging if available)

If 3+ systemic issues are found, halt and fix the root cause before continuing.


Prioritization

Before beginning development, score all tasks using the Sprint Scoring Matrix. See pm-prioritization.md → Sprint Scoring Matrix.

Scoring formula: Business Value × 2 + Risk if Delayed × 1.5 + (Deps Blocked × 1)

Sequencing rules:

  1. Architecture and schema always come first
  2. Data access before services before endpoints (dependency order)
  3. Auth must be implemented before endpoints that require it
  4. Within the same tier: highest score ships first

Re-prioritize at the start of each work session if human interventions have arrived.


MVP Mode Behavior

When Release Mode: MVP in the handoff package, adjust scope and detail:

Aspect Full Production MVP
Endpoints All P0 MVP endpoints only
Testing Full suite Core integration + contract tests

Active Intervention Check

At the start of every work session and before presenting the gate:

  1. Check human-interventions/active/ for files tagged phase: 06-backend-implementation or phase: all
  2. If urgency: immediate — halt current task and process the intervention first
  3. If urgency: end-of-phase — integrate before gate presentation
  4. After resolving, move to human-interventions/processed/ and note in gate summary
flowchart TD
    check[Check human-interventions/active/ for phase: 06-backend-implementation or phase: all] --> found{Files found?}
    found -->|No| proceed([Continue phase work])
    found -->|Yes| urgency{Urgency?}
    urgency -->|immediate| halt[Halt current task Process intervention first]
    urgency -->|end-of-phase| queue[Integrate before gate presentation]
    halt --> archive[Move to processed/ Note in gate summary]
    queue --> archive
    archive --> proceed

Feedback & Update Loop

Receiving feedback

  • From gate REVISE: Fix only the specifically flagged issues — do not refactor unrelated code
  • From human intervention: Assess impact on current sprint tasks, re-run prioritization if scope changes
  • From 04-backend-design (API/schema changes): Resync implementation with updated spec

Propagating updates downstream

  • If API contract changes: create human-interventions/active/[date]-06-api-update/content.md; notify 07-integration
  • If schema changes: document migration path and notify integration
  • If new endpoints added: re-run sprint scoring to fit into priority order

Revision limits

Max 3 revision cycles at this gate. On the 3rd, escalate to orchestrator.


Human Review Gate

After completing all phases, present the development package:

BACKEND IMPLEMENTATION COMPLETE — HUMAN REVIEW REQUIRED

Artifacts produced:
- [ ] Project architecture documented
- [ ] Schema migrations executed
- [ ] Data access layer implemented (repositories)
- [ ] Service layer implemented (business logic)
- [ ] All P0 endpoints implemented
- [ ] Auth and security implemented
- [ ] Error handling and validation consistent
- [ ] Test suite passing (unit, integration, contract)

Sprint prioritization summary:
- Completed: [list tasks in priority order]
- Deferred to next sprint: [list + reason]

Review checklist: see backend-checklist.md

Reply with:
- APPROVED → begin 07 Integration
- REVISE: [feedback] → agent will update and re-present