controlplan

SKILL.md

Control Plan

When to Activate This Skill

  • "Create a control plan for [part/process]"
  • "What inspection frequency for [characteristic]?"
  • "Define control methods for [operation]"
  • "Link PFMEA to control plan"
  • "What's the reaction plan for [out-of-spec condition]?"
  • "Develop prototype/pre-launch/production control plan"

Control Plan Phases

Prototype Control Plan

  • Purpose: Control during prototype build
  • Focus: Dimensional measurements, material tests, performance
  • Frequency: Often 100% on critical dimensions
  • Duration: Until prototype approval

Pre-Launch Control Plan

  • Purpose: Control during PPAP/validation runs
  • Focus: Enhanced inspection, process validation
  • Frequency: Increased sampling, SPC establishment
  • Duration: Until production approval (PSW)

Production Control Plan

  • Purpose: Ongoing production control
  • Focus: Standardized controls, sustained quality
  • Frequency: Based on process capability
  • Duration: Life of production

AIAG Control Plan Format

Required Columns

Column Description Source
Part/Process Number Operation step number Process Flow
Process Name/Description Operation description Process Flow
Machine/Device/Jig/Tool Equipment used Process documentation
Characteristic Number Unique ID for characteristic Sequential
Product Characteristic Part feature being controlled Drawing, spec
Process Characteristic Process parameter affecting product PFMEA
Special Char Class CC, SC, or blank PFMEA/Drawing
Product/Process Spec Tolerance or requirement Drawing, spec
Evaluation/Measurement Gage/method used MSA
Sample Size Quantity inspected Based on risk
Sample Frequency How often inspection occurs Based on risk
Control Method How results are recorded/used SPC, checklist, etc.
Reaction Plan Action when out of spec Defined response

Special Characteristics

Critical Characteristics (CC)

  • Symbol: Shield, (CC), or inverted delta
  • Criteria: Safety or regulatory compliance
  • Requirements:
    • Documented in Control Plan
    • Enhanced inspection (often 100%)
    • SPC required (Cpk ≥1.67)
    • Traceable records
    • Identified on drawing

Significant Characteristics (SC)

  • Symbol: Diamond, (SC)
  • Criteria: Fit, function, appearance significant to customer
  • Requirements:
    • Documented in Control Plan
    • Appropriate inspection frequency
    • SPC recommended (Cpk ≥1.33)
    • Records maintained

Standard Characteristics

  • Symbol: None
  • Criteria: All other characteristics
  • Requirements:
    • Documented in Control Plan
    • Sampling based on risk
    • Records as required

Sample Size and Frequency Guidelines

Based on Severity (from PFMEA)

Severity Sample Size Frequency Rationale
9-10 (Safety) 100% Every piece Safety critical - no escape
7-8 (High) 100% or n≥5 Per hour or per lot High customer impact
5-6 (Moderate) n≥3 Per shift or per setup Moderate risk
1-4 (Low) n≥1 Per lot or periodic Low risk

Based on Process Capability

Cpk Range Typical Frequency Notes
<1.00 100% or very frequent Process not capable
1.00-1.33 Every hour or more Marginal capability
1.33-1.67 Per shift or setup Capable
>1.67 Per setup, daily, or lot Highly capable

Standard Frequency Terms

Term Meaning When to Use
Continuous 100% inspection Safety, high risk
Per piece Every part Critical characteristics
Per hour n pieces every hour SPC, high-risk
Per shift Start and end of shift Setup-sensitive
Per setup At setup only Stable characteristics
Per lot One sample per production lot Low-risk, stable
Daily Once per day Periodic verification
Weekly Once per week Very stable

Control Methods

Inspection Methods

Method Description Typical Use
Visual Operator observation Surface defects, presence
Go/No-Go Gage Attribute check Hole size, thread, profile
Caliper/Micrometer Variable measurement Dimensions
CMM Coordinate measurement Complex features
Height Gage Surface plate measurement Flatness, position
Profilometer Surface finish Ra, Rz
Hardness Tester Material property HRC, HRB
Torque Wrench Fastener torque Assembly
Leak Test Seal integrity Fluid systems
Functional Test Performance verification End-of-line

Recording Methods

Method Description When to Use
Check Sheet Attribute recording Visual checks, presence
Data Log Variable data recording Measurements
SPC Chart Statistical control chart Critical/significant
Traveler Part-specific record Traceability
Electronic MES/database entry High volume
None (process control) Poka-yoke, automated Error-proofed

Reaction Plans

Standard Reaction Plan Format

IF [out-of-spec condition] THEN:
1. STOP - Halt production/segregate suspect
2. CONTAIN - Quarantine affected parts
3. NOTIFY - Alert supervisor/quality
4. EVALUATE - Determine root cause and extent
5. CORRECT - Implement fix before restart
6. VERIFY - Confirm correction effective

Reaction Plan Examples

Dimension Out of Spec:

  1. Stop production
  2. Segregate last good part to current
  3. Notify Quality/Supervisor
  4. Check tool condition, offset, fixture
  5. Adjust/replace as needed
  6. Run first piece, verify to spec
  7. Inspect segregated parts 100%

Visual Defect:

  1. Reject defective part
  2. Assess severity (isolated vs trend)
  3. If trend: notify supervisor, review process
  4. Identify root cause (tool, material, handling)
  5. Implement correction
  6. Resume with enhanced attention

SPC Out of Control:

  1. Mark control chart
  2. Continue production if within spec
  3. Investigate pattern (rule violated)
  4. Identify assignable cause
  5. Implement correction
  6. Document on chart

PFMEA to Control Plan Linkage

Required Flow

PFMEA Item            →    Control Plan Entry
─────────────────          ───────────────────
Process Step          →    Part/Process Number
Function              →    Characteristic
Failure Mode          →    What we're preventing
Detection Control     →    Control Method
S/O/D Ratings         →    Sample Size/Frequency
Special Char          →    Special Char Class

Linkage Verification

For each Control Plan line, verify:

  • PFMEA has corresponding failure mode
  • Special characteristics match
  • Control method addresses PFMEA detection
  • Frequency appropriate for risk level
  • Reaction plan defined

Output Format

When generating Control Plan content:

# Control Plan
**Part Number**: [P/N]
**Part Name**: [Description]
**Customer**: [Customer Name]
**Control Plan Number**: CP-[DEPT]-[SEQ]
**Phase**: [ ] Prototype  [ ] Pre-Launch  [X] Production
**Revision**: [Rev] | **Date**: [YYYY-MM-DD]
**PFMEA Reference**: PFMEA-[XXX]

## Operation: [Number] - [Name]

### Characteristic 1: [Description]

| Field | Value |
|-------|-------|
| **Char No.** | [Unique ID] |
| **Product/Process** | Product / Process |
| **Class** | CC / SC / - |
| **Specification** | [Nominal ± Tolerance] |
| **Evaluation Method** | [Gage/Equipment] |
| **Sample Size** | [n] |
| **Sample Frequency** | [When] |
| **Control Method** | [Recording method] |
| **Reaction Plan** | [Reference or inline] |

Integration with Related Skills

PFMEA

Control Plan is direct output of PFMEA:

  • Every PFMEA detection control → Control Plan method
  • PFMEA severity drives inspection frequency
  • PFMEA updates trigger Control Plan review

Load: read ~/.claude/skills/Pfmea/SKILL.md

MSA

All gages in Control Plan require MSA:

  • Gage R&R for variable gages
  • Attribute agreement for attribute gages
  • MSA acceptance before production approval

Load: read ~/.claude/skills/Msa/SKILL.md

AutomotiveManufacturing

Work instructions must reflect Control Plan:

  • Inspection steps in work instructions
  • Operator-level control methods
  • Quality checkpoints documented

Load: read ~/.claude/skills/Automotivemanufacturing/SKILL.md

Supplementary Resources

For detailed guidance: read ~/.claude/skills/Controlplan/CLAUDE.md

For templates: read ~/.claude/skills/Controlplan/templates/control-plan-template.md

For control method selection: read ~/.claude/skills/Controlplan/reference/control-methods.md

For sampling guidelines: read ~/.claude/skills/Controlplan/reference/sample-frequencies.md

Weekly Installs
4
First Seen
2 days ago
Installed on
claude-code3
windsurf2
trae2
opencode2
codex2
antigravity2